About a mile north of Exit 4 on I-93, a 295-foot bridge crosses the highway and carries a four-lane road with a raised median and traffic signals at both ramp ends. The road is called Old Rum Trail. It has been finished since July 18, 2025, and no traffic has driven on it yet.
If you're comparing Londonderry with Derry, you've probably seen Exit 4A in a listing description or heard it brought up at a showing as something "coming soon." The full timeline tells a different story. The interchange sits in Londonderry, but its first job is to give Derry a new way onto the interstate. For Londonderry, the gain will come mostly through Woodmont Commons and the town's commercial tax base, not through a shorter drive from Londonderry's neighborhoods.
The ramps are done, but Derry's road work comes first
The interchange was the first of three construction phases. New Hampshire DOT will not open it until the second phase, the rebuild of Folsom Road and NH Route 28 in Derry, can carry traffic without getting in the way of its own construction. Weaver Brothers Construction of Bow won that Folsom Road contract with a $31 million bid. Work started in late fall 2024 and is expected to finish in summer 2028.
Here is the schedule according to NHDOT's Fall 2026 project update and local reporting:
| Phase | What it covers | Status or target |
|---|---|---|
| 13065A | Exit 4A ramps, Old Rum Trail bridge, 0.7 miles of Old Rum Trail to the Madden Road area | Finished July 18, 2025, under a $45.5 million contract |
| 13065B | About 0.8 miles of Folsom Road plus part of NH Route 28 in Derry | Construction expected to finish summer 2028, when the interchange can open |
| 13065C | About 1.6 miles of Tsienneto Road to NH Route 102, plus part of the Route 28 Bypass | Design continues into fall 2027, with construction expected to start early spring 2029 |
The Londonderry Times reported in August 2026 that the last Tsienneto Road segment is targeted for completion in fall 2032. The same article put the total project estimate at $161.3 million, up from $50 million in 2015. It also listed what could push the schedule back: utility relocation, the pace of right-of-way purchases, and a court-ordered redesign of a multi-use path underpass near Shields Brook.
Counted from late November 2026, the exit is at least a year and a half from opening, and the full corridor is about six years from being finished. If you buy this winter, you'll likely make many trips on the roads as they are now before Exit 4A changes your route.
Exit 4A leads east into Derry
The interchange connects only to the east side of I-93. Old Rum Trail runs east from the southbound ramps to the Madden Road area and then joins Folsom Road in Derry. According to the Londonderry Times, the exit has no western connection into Londonderry.
NHDOT says the project's purpose is to ease congestion and improve safety on NH Route 102 from I-93 east through downtown Derry. The roads that get the most work are in Derry: Folsom Road east past Pinkerton Street, Crystal Avenue, the Route 28 Bypass, and Tsienneto Road out to Route 102. When the full corridor opens, a Derry homeowner along that route will get a new path to the highway. A Londonderry homeowner west of the interstate will keep using Exit 4 or Exit 5 as they do today.
The part of the project Londonderry residents can see is along the highway. The finished first phase included sound barriers along Trolley Car Lane and Seasons Lane, plus a restored stretch of the Wheeler Brook corridor. If you're touring homes on those streets, the barriers are already up, and the ramps behind them won't carry traffic until the Derry work is far enough along.
Londonderry's gain comes through Woodmont Commons
Town officials have long counted on Exit 4A for something besides commute times. In the Londonderry Times, they described the interchange as key to commercial and industrial growth along Route 28, mainly at Woodmont Commons, the 600-acre mixed-use development that keeps adding residential, medical, commercial and warehouse space.
The paper reported figures from fiscal updates presented to the Planning Board. Woodmont Commons has produced nearly $16 million in net tax revenue for the town since 2013 and now has more than 200 employees. Consultants told the board this spring that the next phase of Woodmont's buildout would benefit significantly once the exit opens.
The next phase is already showing up in town filings. A May 2025 traffic memo filed with the town described a proposed Gateway Commerce Park on Woodmont Commons land, with up to 751,600 square feet of research-and-development and fulfillment space and two driveways onto Old Rum Trail. A June 2025 town staff memo described it as four industrial and warehouse buildings built in phases near the future exit and recommended conditional site-plan approval. On the housing side, the Londonderry Times reported in December 2025 that Procopio Companies had proposed 250 single-family rental homes at 36 Pillsbury Road inside Woodmont Commons, with one- to three-bedroom homes, a clubhouse, a dog park and walking paths.
This matters to a homeowner because of where the money goes. Woodmont's nearly $16 million in net tax revenue since 2013 came into the same town budget that every Londonderry household pays into, and Exit 4A points straight at the land where Woodmont's next commercial buildings are proposed. For more on how Londonderry's tax bill compares with nearby towns, see our look at Londonderry's property taxes. If you buy in Londonderry, the exit's biggest effect on you is likely to be on the town's revenue, not on your drive to work.
How both towns' markets look before the exit opens
The latest town-level reports from New Hampshire REALTORS show two closely matched markets on either side of the future interchange.
In Londonderry, single-family homes had a year-to-date median sale price of $710,000 through October 2026, up 2.2% from the same period in 2025, across 174 closed sales. October by itself came in at a $630,000 median on 25 sales. The report notes that small samples can make percent changes look extreme, so the year-to-date figure is the better guide. Londonderry homes that sold in October 2026 spent a median of 14 days on market, and sellers received 99.7% of their original list price.
In Derry, the October 2026 single-family median was $622,500 on 22 sales, with 18 days on market.
| October 2026, single-family | Londonderry | Derry |
|---|---|---|
| Median sale price | $630,000 | $622,500 |
| Closed sales | 25 | 22 |
| Days on market until sale | 14 | 18 |
| Inventory at month-end | 23 | 37 |
| Months of supply | 1.3 | 1.7 |
Supply grew in both towns. Londonderry had 23 single-family homes for sale at the end of October 2026, up from 12 a year earlier, and its year-to-date new listings through October were up 30.2%. Derry's inventory rose to 37 homes over the same period.
Both towns are still moving fast, with fewer than two months of supply and homes going under contract in two to three weeks. All of those sales happened while the exit was closed, so every price in these reports reflects the roads as they work today. If a seller points to Exit 4A to justify a price, especially for a home west of I-93, ask which direction the exit actually serves. The answer is east, into Derry.
The legal challenge is settled
In October 2026, NHPR republished an Eagle-Tribune report that a jury had unanimously sided with the state in a challenge to land taken for the project in the Folsom Road area. The jury found that the takings served a public purpose, were reasonably necessary, and would produce a net public benefit. The same report repeated the state's timeline: Folsom Road finishes in summer 2028, and Tsienneto Road construction starts in spring 2029.
With that case decided, the remaining schedule risks are the construction issues NHDOT has listed: utilities, right-of-way purchases and the Shields Brook path redesign. If you're planning to stay five years or more, the exit will probably open while you live there. If you're planning on three years, judge the house by the commute you'd have now.
Your Exit 4A questions, answered
Can I use Exit 4A to get from Londonderry to I-93 when it opens? The interchange connects only east of the highway, through Old Rum Trail into Derry. It has no western connection into Londonderry.
When will Exit 4A open? NHDOT ties the opening to the Folsom Road phase in Derry, which is expected to finish in summer 2028.
Does Exit 4A change anything on Route 102? Easing congestion on Route 102 through downtown Derry is the project's stated purpose. The Tsienneto Road and Route 102 work is in the last phase, with construction expected to start in early spring 2029.
If you're weighing a home in Londonderry against one in Derry and want to know which side of the Exit 4A timeline works for your plans, Granite State Realty Group can walk you through the commute, the comparable sales and the Woodmont Commons pipeline for the specific streets on your list. Request a free local market consultation, and we'll start with the roads you'll actually drive.